Still Using Velocity? Make It Useful Again

In our previous post, we examined how velocity is often misinterpreted.

  • Averages become commitments
  • Story points turn into deadlines
  • And we lose sight of what estimation is really for, helping better conversations happen

If you missed it, start here – Velocity. It’s Not What You Think It Is. That post built on our opening piece, Agile Estimation Is Not Broken. The Thinking Is.

Now that we have laid that groundwork, we meet teams where they are and help them grow from there.

Many teams still track velocity, still use release burndowns.

Are these great tools? No, there are better ways.
But what is familiar gives us a way in.

Shift the Conversation

Instead of relying on an average, we apply what we know about uncertainty:

  • Best case
  • Typical case
  • Worst case

Suddenly, velocity becomes a forecast. Not a fixed plan.

And we go from asking if we will hit the date to:

  • What are we confident will get done
  • What is at risk
  • What trade-offs are we willing to make

It is not about being perfect. It is about bringing more transparency and collaboration.
So we can have better conversations around expectations, value and risk.

Make the Work Visible

We often see teams using release burndowns. But instead of treating them as fixed plans or status reports, we combine them with a cone of uncertainty.

Release burndown with cone of uncertainty

This small change helps shift the conversation:

  • If we are trending in the red, that tells us what is at high risk
  • If we are inside the cone, that is where we have higher confidence, if nothing major changes
  • It is not about certainty. It is about making risk visible, setting expectations, to enabling collaboration

Now the burndown becomes a conversation about expectations, value and trade-offs.
Not just delivery pace.

Use What You Already Have

If your team has used velocity for a while, you already have historical data.
You can use that data better by asking:

  • What was our lowest Sprint velocity
  • What was our typical range
  • What was our highest

This is not perfect. However, it provides a starting point for forecasting using ranges instead of fixed numbers.

From Velocity to Flow

This approach helps shift the conversation away from effort and toward uncertainty and value.

Once that happens, we can go further.
We can help teams move beyond velocity and explore better ways to forecast using actual delivery data like throughput and flow.

We know where we want teams to go.
But change does not happen overnight.

Sometimes, a few well-timed nudges and some mindset shifts are all it takes.

Coming Next

Perhaps story points and velocity were never the most effective way to forecast.
In our next post, we will share a simple experiment to help teams rethink estimation and move forward.

Stay in the loop on all things agile

Make sure you do not miss out on any news! Join our mailing list for a monthly newsletter bursting at the seams with need-to-know information about b-agile and the industry!

  • This field is for validation purposes and should be left unchanged.

By completing this form you are agreeing to our privacy policy